HCAL Meetings: December 1995 CMS Week
Date: Mon, 06 Nov 1995 11:10:33 EST
From: skuja@umdhep.umd.edu
Subject: Preliminary HCAL agenda for CMS week
********************************************************************************
Dear Colleagues:
I enclose a preliminary agenda for the December CMS week. I have been
requested by the HB/HF technical managers to hold a meeting on Sunday,
December 3. If you want to give a presentation or make suggestions for
presntations please let me know soon. The agenda is PRELIMINARY and
subject to change.
Please note that the presentations of the HV technologies (PPC/QF) to the
Forward Hadron Calorimeter Evaluation and Advisory committee
(Denegri, Green, Pauss, Virdee) will take place during the week of
November 27 at CERN. These presentations and subsequent discussions will
be public to CMS members at the discretion of the Evaluation and Advisory
Committee. It is my hope that the HV working groups can come to a
consensus with the aid of the Evaluation Committee. The entire HCAL IB will
meet on Monday, December 4 to express their support for the
designated technology.
Andris Skuja
CMS HCAL IB Chair
%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%
HV Presentations:
November 27 through December 3
(organized by Denegri, Green, Pauss, Virdee)
The HV presentations and discussion are open to the CMS
membership at the discretion of the organizing committee.
All HCAL IB members who desire to participate in the HV
discussion should attend the open presentations and discussion.
HCAL meeting, CMS Week, CERN, Geneva, Switzerland (Dec 3 through Dec 8)
Sunday, December 3: Central Calorimeter (HB/HF) (open)
(chaired by A. Skuja / organized by Freeman/Kryshkin)
10:00 Status of HB Project (Freeman)
10:30 Status of H2 and H4 test beam work (Freeman/de Barbaro)
11:00 Status of HB Project (Golutvin/Kryshkin)
11:30 Status of H2 and H4 test beam work (Kryshkin/others)
12:00 Future test beam efforts -- discussion (Freeman/Kryshkin)
12:30 Future efforts -- discussion (Skuja)
13:00 Lunch
14:30 Status of HB simulation work (Kunori)
15:30 Status of HCAL simulation work (Genchev/others)
Monday, December 4: HCAL IB (HB/HF/HV) (closed - CMS membership only)
(chaired by A. Skuja)
9:00 Presentation of HV technology decision
(Denegri, Green, Pauss, Virdee)
11:00 Coffee Break
11:30 Discussion
Monday, December 4: HCAL IB (HB/HF/HV) (closed - CMS membership only)
(chaired by A. Skuja)
14:00 Discussion continues (if necessary)
16:00 Coffee break
16:30 HCAL(HB/HF/HV) IB constitution
Discussion of next election of HCAL IB officers
Tuesday, December 5: HCAL/ECAL interface (open)
(organized by J.-L. Faure' and A. Skuja)
9:00 Status of ECAL mechanical engineering design (Cockerill/others)
10:00 Status of ECAL electronics layout (Denes/others)
11:00 Simulation of ECAL/HCAL interface (Kunori/others)
11:30 Implications of ECAL/HCAL interface on Calorimeter trigger
(Smith/Rusack/others)
11:30 Discussion
Tuesday, December 5: HCAL engineering
(chaired by A. Skuja)
14:00 Status of Engineering (Churin)
14:30 HB Wedge design (Freeman)
15:00 HB Wedge FEA: Maryland report (Skuja)
15:30 Other Alternatives to an EBW Barrel (Li ??)
16:00 Cable/Fiber/Source tube layout
16:30 HF mechanical design (Kryshkin/others)
Wednesday, September 27: Integration meeting
(chaired by A. Herve')