US CMS Project Management Plan                           DRAFT: May 9, 1995

Table of Contents

  • 1. US CMS Organization
  • 1.1 Membership
  • 1.2 Collaboration Board
  • Meetings
  • Voting
  • Elections
  • Elective Offices
  • Competence
  • 1.3 Management Board
  • Spokesperson
  • CMS Management Representatives
  • US Subsystem Representatives
  • Technical Representatives
  • Funding Agency Liaisons
  • Project Management Representatives
  • 2. Project Description
  • 3. Project Management Structure
  • 4. Environment, Safety and Health
  • 5. Work Breakdown Structure and Cost Estimate
  • 6. Project Schedule and Milestones
  • 7. Tracking and Reporting
  • 8. Project Reviews
  • 9. Quality Assurance
  • Appendices
  • Appendix A: US CMS Institutions and Members
  • Appendix B: US CMS Management Board
  • Appendix C: CMS Management Board
  • Appendix D: US CMS Subsystem Participation
  • Appendix E: CMS Technical Board
  • Appendix F: CMS Finance Board