US CMS

Contingency Analysis

Procedures

September 26, 1996


This document details the contingency analysis procedures for

the US CMS WBS elements. The material is extracted from the

US CMS Cost and Schedule Procedures draft of June 30, 1994.


Contingency Analysis

1. Risk Analysis

Risk analysis is to be performed for each WBS element. Results of this analysis will be related to a contingency which will be listed for each WBS element. The goal is to make the method of cost estimation and contingency determination uniform across all WBS elements.

2. Procedures

a. Base Cost Estimate

The base cost estimate is the estimated cost of doing things correctly the first time, unless from past experience you are fairly certain that it will take more than once. In other words, contingency should not be included in the base cost.

b. Cost Contingency

Cost contingency is the amount of additional money, above and beyond the base cost, that is required to ensure the project's success. This money is to be used only for omissions and the unexpected difficulties that may arise. Contingency is held entirely by US CMS project management and not by individual subsystem managers or coordinators. Contingency costs are explicitly part of the total cost estimate.

c. Contingency Estimation

The procedure for estimating cost contingency is to:

1) Compare the conceptual state of the element with Table 1 to determine risk factors;

2) Compare the potential risk within an element with Table 2 to determine the appropriate weighting factors;

3) Multiply the individual risk factors by the corresponding weighting factors, and then sum them to determine the composite contingency percentage;

4) Do this for each element at a chosen level, preferably level 5 or 6 of the WBS;

5) Calculate the dollar amount of contingency for an element by multiplying the base cost by the calculated contingency percentage.

Table 1

Technical, Cost, and Schedule Risk Factors
Technical Cost Schedule Risk Factor
Existing design and off the shelf hardware Off the shelf or catalog item Not used 1 %
Minor modifications to an existing design Vendor quote from established drawings No schedule impact on any other item 2 %
Extensive modifications to an existing design Vendor quote with some design sketches Not used 3 %
New design,

nothing exotic

In-house estimate based on previous similar experience Delays completion of non-critical path subsystem item 4 %
New design, different from established designs or existing technology In-house estimate for item with minimal experience but related to existing capabilities Not used 6 %
New design, requires some R&D but does not advance the

state-of-the-art

In-house estimate for item with minimal experience and minimal in-house capability Delays completion of critical subsystem item 8 %
New design, development of new technology which advances state-of-the-art Top-down estimate from analogous programs Not used 10 %
New design, way beyond the current state-of-the-art Engineering judgment Not used 15 %

Table 2

Technical, Cost, and Schedule Risk Weights
Technical Cost Schedule Risk Weight
Not used
Material cost OR Labor rate Same for all 1
Design OR Manufacturing Material cost AND Labor rate Not used 2
Design AND Manufacturing Not used Not used4

3. Input Format

In a spreadsheet format, create a copy of your WBS. Pick a level at which you will do detailed contingency analysis, and include the following additional columns:

WBS #
Elem. Desc.
Tech Risk
Cost Risk
Sched. Risk
Tech Wt.
Cost Wt.
Sched. Wt.
Comp. Risk %

Input all information following the procedure outlined above.

Example: (from the SDC Si Tracker)

WBS #
Elem. Desc.
Tech Risk
Cost Risk
Sched. Risk
Tech Wt.
Cost Wt.
Sched. Wt.
Comp. Risk %
1.1.1.4.1Cooling Rings
6
4
8
4
2
1
40
1.1.1.4.2Bridge Struc.
4
4
4
4
1
1
24
1.1.1.4.3Coolant Distr.
4
3
4
2
2
1
18

A more detailed example is provided in the Appendix.

4. Backup Information

Keep all supporting information used in deriving risk factors. Most of the backup information will be the above spreadsheet itself.