Contingency Analysis Example

WBS Number WBS or Activity Description Tech. Risk Cost Risk Sched. Risk Tech. Wt. Cost Wt. Sched. Wt. Contingency (%)
4.2 . 0
4.2.1 Refrigeration Systems 0
4.2.1.1 Helium Refrigerator 4 3 8 4 2 1 30
4.2.1.2 Liquid Nitrogen System 0
4.2.1.2.1 Liquid Nitrogen Dewar 4 4 4 2 2 1 20
4.2.1.2.2 Valves & Instrumentation 4 4 4 2 2 1 20
4.2.1.2.3 Pumps, Subcoolers & Other Equipment 4 6 4 2 2 1 24
4.2.1.3 Control System 4 6 4 2 2 1 24
4.2.1.4 Assembly & Test 4 4 4 4 2 1 28
4.2.1.5 Safety Report 4 6 4 2 1 1 18
4.2.1.6 Management & Integration 4 6 4 2 1 1 18
4.2.2 Transfer Systems 0
4.2.2.1 Cryogenic Transfer Line 0
4.2.2.1.1 End Cans 4 4 4 2 2 1 20
4.2.2.1.2 Expansion Boxes 4 4 4 2 2 1 20
4.2.2.1.3 Transfer Line Sections 4 4 4 2 2 1 20
4.2.2.1.4 Assembly & Test 4 4 4 4 2 1 28
4.2.2.2 Gas Piping System 4 6 4 2 2 1 24
4.2.2.3 Electrical Buss System 4 6 4 2 2 1 24
4.2.2.4 Water Systems 4 6 4 2 2 1 24
4.2.2.5 Control System 4 6 4 2 2 1 24
4.2.2.6 Safety Report 4 4 4 2 1 1 16
4.2.2.7 Management & Integration 4 4 4 2 1 1 16
4.2.3 Auxilliary Cryogenic Support Systems 0
4.2.3.1 Cryogenic Equipment for VLPCs 4 6 4 4 2 1 32
4.2.3.2 Equipment for Nitrogen Purging 4 6 4 4 2 1 32