1. Introduction
This Statement of Work (SOW) is made to provide the yearly details
of the work agreed to between US CMS and the US CMS group at <Institution>.
It covers the specific period of performance from October 1, 1997
through September 30, 1998.
2. Personnel
2.1. List of Scientific Personnel
Participating scientists with anticipated fraction of their research
time committed to CMS during this period of performance are listed
below. No support for these individuals comes from project funds.
| Name | CMS
Fraction | Other Research
Commitments/Comments |
2.2. List of Technical Personnel
Participating technical personnel with the anticipated fraction
of their time (time fractions are estimates and are not cost shares)
committed to CMS during this period of performance and their source(s)
of support are indicated below. The possible sources are DUS =
DOE, US CMS Project; NUS = NSF, US CMS Project; DBG = DOE base
grant; NBG = NSF base grant, UID = university infrastructure,
DOE-supported group; and UIN = university infrastructure, NSF-supported
group as shown in the WBS.
Engineers
Name | CMS
Fraction | Cost on CMS Project | Source of Support |
Designers
Name | CMS
Fraction | Cost on CMS Project | Source of Support |
Technical Specialists
Name | CMS
Fraction | Cost on CMS Project | Source of Support |
Programmers
Name | CMS
Fraction | Cost on CMS Project | Source of Support |
Others
Name | CMS
Fraction | Cost on CMS Project | Source of Support |
2.3. Other Key Personnel
The Environment, Safety and Health officer for <Institution>
currently responsible for compliance with applicable ES&H
policies associated with CMS participation by this institution
is <ES&H Name> of <Institution>. The Quality
Assurance officer for the US CMS group at <Institution>
currently responsible for QA compliance of tasks performed by
this institution is <QA Name> of <Institution>. [Persons
identified in this section are typically ES&H and QA professionals
who provide assistance to line personnel responsible for CMS activities.]
3. Responsibilities for this Period of Performance
3.1 WBS Items at L7, Estimated Cost and Deliverable
During this period of performance the US CMS group at <Institution>
agrees to supply the following deliverables at a cost not to exceed
the estimated base cost given in the US CMS WBS. The following
itemized list describes the items (or partial completion of items)
provided in this period (Statements of Work).
| WBS (L7) | Task - Deliverable | WBS Base Cost | FY98 Cost | FNAL MPO | DOE Suppl. | NSF |
| Total | Requested FY98 funds ($k) |
3.2. Coordination and Reporting
The US CMS Level 2 Manager for the <subsystem> subsystem
is <name1>. The institution contact person for <subsystem>
activities at <Institution> is <name2>. The task managers
for <subsystem> activities carried out by the US CMS group
at <Institution> are as follows:
Task Task Manager
3.3. Procurement Authorization
Item purchases exceeding the delegated limit (currently $10k)
must be authorized in advance of obligation by the US CMS Level
2 manager. Major procurements (currently $100k) must in addition
have the written authorization of the US CMS Technical Director
and Construction Project Manager. Items purchased as CMS Common
Project items must be explicitly authorized by the US CMS Technical
Director and Construction Project Manager and approved by the
CMS Resource Manager, regardless of the cost.
3.4. Reporting to US CMS Project Management
The US CMS group at <Institution> will report all CMS related
expenditures and labor charges together with associated technical
progress in each item of work by Work Breakdown Structure (WBS)
category (Level 7) .
Technical progress will be reported by WBS element L4 to the Level 2
Manager and the Construction Project Manager on a quarterly basis
and will cover all items covered in this Statement of Work regardless
of the specific nature of the funding support.
The US CMS group at <Institution> agrees to furnish complete
documentation of the quality control and performance checks which
are carried out for US CMS in the performance of this work.
The US CMS group at <Institution> agrees to maintain a ledger
of a form specified by US CMS Project Management.
3.5. Collaboration with Other Groups and Institutions
Design, construction and installation related to the <subsystem>
subsystem will be carried out in close communication and collaboration
with other groups working on this and related subsystems.
WBS / Task (L4) | Collab.
Group | Responsibility with US CMS group at <Institution> |
4. Contribution of Effort, Services and Equipment
Subject to adequate funding by DOE or NSF, the US CMS group at
<Institution> will provide support for the scientific and
technical personnel as indicated in section 2 during this period
of performance. This contribution refers only to support provided
outside the US CMS Project.
5. Fermilab (as host institution) Effort, Services and Facilities
Tracking of Fermilab CMS support, whether provided by Fermilab
or paid by the US CMS Project, will be done using appropriate
effort reporting codes. The costs incurred will be reported to
the Fermilab Director.
Contributing Fermilab personnel with the anticipated fraction
of their time committed to CMS during this period of performance
and their source(s) of support are:
5.1. Administrative Staff
Name | CMS
Fraction | Source of Support |
5.2. Engineers
Name | CMS
Fraction | Source of Support |
5.3. Designers
Name | CMS
Fraction | Source of Support |
5.4. Technical Specialists
Name | CMS
Fraction | Source of Support |
5.5. Programmers
Name | CMS
Fraction | Source of Support |
5.6. Others
Name | CMS
Fraction | Source of Support |
6. Costs and Funding
A total amount of $<x,xxx>k will be provided to cover work
for the initial period. Any remaining funds needed to complete
the tasks described above will be provided subject to availability
of funding and performance during the initial period. Management
control requires the review and concurrence of the Level 2 Manager
and the Technical Director and Construction Project Manager, as
needed, for major expenditures, as defined above. The release
of funds above the given thresholds will be contingent upon this
concurrence.
7. Schedules and Milestones
The US CMS group at <Institution> will make every effort
to carry out their institutional responsibilities consistent with
the overall CMS schedule. In this Statement of Work are listed
the program milestones for this period of performance.
The program milestones for this period of performance relevant
to the US CMS group at <Institution> are listed here:
Program Milestones | Baseline
Milestone Date | Current
Milestone Date |
8. Makers and Concurrence
The following persons concur in the terms of this Statement of
Work. These terms will be updated as appropriate in later Statements.
Makers of this Memorandum:
Dan Green <date> <Name> <date>
US CMS Technical Director US CMS Group Principal Investigator
<Institution>
Ed Temple <date> <Name> <date>
US CMS Construction Project Manager Grants/Contracts Officer
<Institution>
<Name> <date> <Name> <date>
US CMS Level 2 Manager Procurement/Purchasing
<Subsystem> Subsystem Department Representative
<Institution>
Concurrence:
Ken Stanfield <date>
Deputy Director
Fermilab
Copy sent to:
Ernst Radermacher <date>
CMS Technical Coordinator