Date: Wed, 18 Feb 1998 14:38:05 -0500 (EST) From: skuja@umdhep.umd.edu Subject: Proposed Schedule for HCAL Lehman Review Preparations Dear Colleagues: I propose the following schedule for preparing for the Lehman review (Remember that we have a internal review at FNAL as well the preparation for the Lehman sessions). Friday, Feb 20 & Saturday, Feb 21: Absorber & Optics +++++Saturday, March 7 to Friday, March 14: CMS Plenary Week at CERN March 7 and March 8: HCAL plenary meeting March 9: HCAL Engineering & HCAL IB March 10: Test beam (am); Calibration (pm); HF (all day) March 11: Integration Friday, March 20 to Thursday, March 26: Review of all subsystems at FNAL (finalize costs and schedule) March 20: Trigger/DAQ March 21: Electronics, Controls, HV March 22: Costs & Schedule (???) March 23: HPD's & Boxes March 24: Calibration March 25: HF March 26: PPP's & Remainder +++++++++ NOTE: We have to provide a hard copy of our presentation to the CMS management by March 31 April 3 to April 6: Preparation for Internal Review April 3 & April 4: Dry Run April 5 & April 6: Modified Presentations April 7 - 9: Internal Review: Preparation for the Lehman Session +++++April 17 & April 18: US CMS ANNUAL Meeting at Gainsville Friday, April 17: HCAL Subsystem meeting Saturday, April 18: US CMS Plenary Session +++++NOTE: Hard Copy of Presentation due April 20 (?) +++++Videoconferencing for individual presentations may be necessary during this time period. May 1 to May 4: Preparation for Lehman Review May 1 & May 2: Dry Run May 3 & May 4: Modified Presentations May 5 - 8: Lehman Review